ORACLE R12 IMPLEMENTATION

Images

ORACLE R12 IMPLEMENTATION

Executive summary

Owner driven actions to mobilise, de-risk and deliver an Oracle R12 implementation with clear responsibilities, checkpoints and outcomes without prescribing specific timelines.

Governance and sponsorship

  • Confirm executive sponsor — Name, authority, escalation path and expected decision turnaround.
  • Establish steering committee — Members, decision rights and reporting cadence.
  • Appoint project owner and PM — Single accountable owner and day-to-day delivery manager.
  • Define success metrics — Select measurable KPIs such as month-end close days, invoice days outstanding, reconciliation exceptions and SLA adherence.
  • Approve budget envelope — Baseline budget, contingency reserve and commercial sign-off thresholds.
About Images

Scope, Landscape, and Design

  • Finalize scope — Define modules, legal entities, ledgers, countries, third-party systems, and deprecated features.
  • Complete customization inventory — Catalogue all custom code, classify as Retain / Refactor / Replace / Retire, and assign accountable owners.
  • Map integrations — Document all interfaces, data flows, middleware components, ownership, and expected transaction throughput.
  • Confirm data scope — Identify master data sets, open transactions, historical balances for migration, and archival policies.
  • Agree on localization requirements — Capture country-specific tax rules, statutory reporting needs, and regulatory dependencies.

Migration Strategy and Cutover Planning

  • Select migration approach — Decide between phased wave deployment or big-bang cutover with rationale and high-level wave plan.
  • Define cutover sequencing — Establish data load order, interface start/stop points, reconciliation checkpoints, and rollback criteria.
  • Specify parallel run strategy — Outline scope, reconciliation sign-offs, and go/no-go decision criteria.
  • Document contingency and rollback plans — Define clear triggers, roles, responsibilities, and fallback procedures.

Data Conversion and Validation

  • Approve source-to-target mappings — Validate mappings for chart of accounts, tax codes, units of measure, and item masters.
  • Execute data cleansing activities — Remove duplicates, correct inactive or erroneous records, and reconcile master balances.
  • Develop conversion scripts and validation checks — Automate reconciliation for trial balance, AR/AP, inventory valuation, and fixed assets.
  • Establish archive and access plan — Define R12 read-only access model and historical reporting procedures.

Build, Testing, and Environment Management

  • Deploy core configuration baseline — Set up ledgers, legal entities, chart of accounts, and security roles in non-production environments.
  • Define testing strategy and entry/exit criteria — Cover unit, integration, regression, performance, and UAT phases with named owners.
  • Prepare representative test data — Define data masking rules, volumes, and refresh cadence per environment.
  • Plan dress rehearsals — Conduct full end-to-end dry runs, including data loads, interface validations, and reconciliation checkpoints.

Change Management, Training, and Runbooks

  • Nominate super-users and trainers — Define role lists, training curriculum, and acceptance benchmarks.
  • Deliver role-based training — Conduct hands-on sessions, process walkthroughs, and train-the-trainer programs.
  • Produce operational runbooks and SOPs — Document Day-1 operations for finance, supply chain, and IT support.
  • Create stakeholder communications plan — Set up regular updates, escalation channels, and readiness dashboards.

Support Model and Stabilization

  • Define hypercare framework — Establish war-room setup, escalation matrix, triage protocols, and ownership for hotfixes.
  • Agree on support tiers and SLAs — Document incident response times, resolution SLAs, and peak support coverage.
  • Set up continuous improvement backlog — Capture defects, prioritize enhancements, and define release cadence.
  • Plan knowledge transfer — Conduct handover sessions, share documentation, and assign ownership of runbooks.

Risks, Controls, Compliance, and Reporting

  • List top risks with owners and mitigations — Include detection triggers, escalation routes, and contingency actions.
  • Implement data privacy controls — Ensure masking in test environments, access control enforcement, and audit logging.
  • Establish change control process — Formalize approvals for configuration, code, and interface changes with full traceability.
  • Set up KPI reporting pack — Define operational and business KPIs with assigned owners and reporting frequency.

Immediate Mobilization Deliverables

  • Signed project charter and KPI sheet.
  • Completed customization inventory with assigned owners.
  • Integration map with owners and contact information.
  • Sample data conversion results with reconciliation checks.
  • Environment access matrix and cutover blackout calendar.